Overall Project View

Club House

A – BLOCK: All the major finishing's are completed and soft handover for interiors in progressing in full swing.

B – BLOCK: All the major finishing's are completed and soft handover for interiors in progressing in full swing.

C – BLOCK: All the major finishing's are completed and soft handover for interiors in progressing in full swing.

D – BLOCK: Structure completed.

E – BLOCK: Structure completed.

Swimming pool water proofing works are under progress

Amphitheatre, jogging track and ancillary works are under progress