PROJECT
PROGRESS

Click on the images to enlarge

A - Block

7th Floor Shuttering Under Progress.

B - Block

Structure Completed

C - Block

Structure Completed.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

27th floor shuttering under progress.

G - Block

Structure Completed.

Internal flat flooring and dado works.
Internal flat flooring and dado works.
Terrace water proofing
Internal punning finishings.
Terrace water proofing

Basement finishings

Basement finishings

Basement finishings

More Details

Click on the images to enlarge

A - Block

Structure Completed.

B - Block

Structure Completed

C - Block

26th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

25th floor shuttering under progress.

G - Block

Structure Completed.

Basement finishings
Basement finishings
Basement finishings
More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

23rd floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

22nd floor shuttering under progress.

G - Block

Structure Completed.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

19th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

18th floor shuttering under progress.

G - Block

Structure Completed.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

17th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

15th floor shuttering under progress.

G - Block

24th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

14th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

13th floor shuttering under progress.

G - Block

22nd floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

12th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

11th floor shuttering under progress.

G - Block

20th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

9th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

8th & 9th floors shuttering under progress.

G - Block

17th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

6th floor shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

7th floor shuttering under progress.

G - Block

14th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

3rd & 4th floors shuttering under progress.

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

6th & 7th floors shuttering under progress.

G - Block

12th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Structure Completed

C - Block

2nd Floor Shuttering Under Progress

D - Block

Structure Completed

E - Block

Structure Completed

F - Block

6th Floor Shuttering Under Progress

G - Block

10th Floor Shuttering Under Progress

More Details

Click on the images to enlarge

B - Block

26th floor shuttering under progress.

C - Block

1st floor shuttering under progress.

D - Block

Structure completed.

E - Block

28th floor shuttering under progress.

F - Block

5th & 6th floors shuttering under progress.

G - Block

7th floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

24th floor shuttering under progress.

C - Block

1st floor shuttering under progress.

D - Block

28th floor shuttering under progress.

E - Block

26th floor shuttering under progress.

F - Block

4th & 5th floors shuttering under progress.

G - Block

5th& 6th floors shuttering under progress.

More Details

Click on the images to enlarge

B - Block

22nd floor shuttering under progress.

C - Block

1st floor reinforcement & shuttering under progress.

D - Block

26th floor shuttering under progress.

E - Block

25th floor shuttering under progress.

F - Block

3rd & 4th floors shuttering under progress.

G - Block

3rd & 4th floors shuttering under progress.

More Details

Click on the images to enlarge

B - Block

20th floor shuttering under progress.

C - Block

1st floor reinforcement under progress.

D - Block

25th floor shuttering under progress.

E - Block

23rd floor shuttering under progress.

F - Block

3rd floor shuttering under progress.

G - Block

2nd floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

18th & 19th floors shuttering under progress.

C - Block

Ground floor reinforcement under progress.

D - Block

23rd floor shuttering under progress.

E - Block

21st floor shuttering under progress.

F - Block

2nd floor shuttering under progress.

G - Block

2nd floor reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

16th floor shuttering under progress.

C - Block

Podium reinforcement under progress.

D - Block

20th floor shuttering under progress.

E - Block

18th floor shuttering under progress.

F - Block

2nd floor shuttering under progress.

G - Block

1st floor reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

13th & 14th floors shuttering under progress

D - Block

17th & 18th floors shuttering under progress.

E - Block

15th floor shuttering under progress

F - Block

1st & 2nd floors shuttering under progress

G - Block

Ground & 1st floors shuttering under progress

More Details

Click on the images to enlarge

B - Block

12th floor shuttering under progress

D - Block

15th floor shuttering under progress

E - Block

14th floor shuttering under progress

F - Block

1st floor shuttering under progress

G - Block

Ground floor shuttering under progress

More Details

Click on the images to enlarge

B - Block

11th floor shuttering under progress

D - Block

12th & 13th floors shuttering under progress.

E - Block

11th & 12th floors shuttering under progress.

F - Block

1st floor shuttering under progress.

G - Block

Ground floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

9th floor shuttering under progress

D - Block

10th floor shuttering under progress.

E - Block

10th floor shuttering under progress.

F - Block

1st floor shuttering under progress.

G - Block

Ground floor shuttering under progress.

More Details

Click on the images to enlarge

B - Block

7th floor shuttering under progress.

D - Block

8th floor shuttering under progress.

E - Block

8th floor shuttering under progress.

F - Block

1st floor shuttering under progress.

G - Block

Podium reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

4th floor shuttering under progress.

D - Block

5th floor shuttering under progress.

E - Block

5th floor shuttering under progress.

F - Block

Ground floor slab under progress.

G - Block

Basement-2 slab under progress.

More Details

Click on the images to enlarge

B - Block

2nd floor shuttering under progress.

D - Block

2nd floor shuttering under progress.

E - Block

2nd floor shuttering under progress.

F - Block

Ground floor slab under progress.

G - Block

Basement-2 reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

1st floor shuttering under progress.

D - Block

2nd floor reinforcement under progress.

E - Block

2nd floor reinforcement under progress.

F - Block

Ground floor reinforcement under progress.

G - Block

Basement-2 reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

1st floor reinforcement under progress.

D - Block

1st floor shuttering under progress.

E - Block

1st floor shuttering under progress.

F - Block

Ground floor reinforcement under progress.

More Details

Click on the images to enlarge

B - Block

Ground floor slab shuttering under progress.

D - Block

1st floor reinforcement under progress.

E - Block

1st floor reinforcement under progress.

F - Block

Basement-1 shuttering under progress.

More Details

Click on the images to enlarge

B - Block

Ground floor shuttering under progress.

D - Block

Ground floor shuttering under progress.

E - Block

Ground floor shuttering under progress.

F - Block

Basement-1 shuttering under progress.

More Details